| Project |
: |
Drainage and Foundations |
| Client |
: |
Interserve Project Services |
| Value |
: |
£90,000 |
| Duration |
: |
9 weeks |
The contract involved installing approximately 150m of clay foul drainage,
over 300m of plastic surface water drainage and 200m of filter drains
with associated oil interceptors and silt traps. Pipe diameters varied
from 100mm up to 300mm with invert levels over 2m deep.
The drainage services a new factory unit, office and external yards.
Substantial savings were made by the Main Contractor by Northern Consruction
Solutions value engineering the scheme and using alternative materials
to those specified.
The job was completed successfully over a seven week period on a compact
site, working alongside other subcontractors and liaising closely with