| Project |
: |
Pallet Store Floor Slab |
| Client |
: |
Lumsden & Carrol |
| Value |
: |
£23,000 |
| Duration |
: |
2 weeks |
The contract required Northern Construction Solutions to construct a
new floor slab within the confines of an existing warehouse unit at Federation
Brewery’s Gateshead site. This work was part of the refurbishment
programme for the Brewery to provide additional storage for pallets on
the site.
The project consisted of the trimming of existing sub-base material to
within the required tolerance, followed by the placing of a 200mm thick
mesh reinforced concrete slab over the 850m² area.
Value Engineering of the job enabled the original minimum of two concrete
pours to be reduced to one, therefore providing the client with a saving
on their programme.
|